RTGC Dismantling, Erection, Relocation and Commissioning Project

Project Name :RTGC Dismantling, Transportation, Erection and Commissioning

Location : Ludhiana to Kathuwas

Scope of Work

  1. PerformanceTesta) Performance Test with Load
    b) Performance Test without load

2. Electrical cable sorting and tagging

3. Mechanical Equipment Dismantling

  •  Spreader With Head block Dismantling
  • Platform & Engine exhaust pipe dismantling
  • E-Room and Engine House Dismantling
  • Jib Crane Dismantling
  •  Trolley Dismantling
  •  Dismantling Of C- Structure
  •  Resting Over Pre-Fabricated stool

4. Loading and Transportation

5. Unloading at Kathuwas

6. Inspection of all components and segregation

7. Cable Laying Over the C-structure

8. Physical Measurement and arrangement for erection of c- structure

9. Erection of C-Frame with bogies

10. Erection of E-room and engine room

11. Fixing of tie rod

12. Trolley Erection and alignment

13. Jib crane Erection

14. Termination of cables

15. Rope Reeving

16. Commissioning and trial with load and without load of RTGC L1 & L2

17. Job Completion Certificate, Job Safety Analysis